SNAPSHOT: Delivering reliable temporary power for a major bioenergy construction and commissioning project requiring an uninterrupted power supply for critical loads.
Customer
Delorean Corporation Limited (DEL)
Application
Construction, Manufacturing
Location
Lilydale VIC
THE BRIEF
Problem We Helped Solve
During early construction and commissioning of the food-waste-to-energy facility in Victoria, grid power was unavailable. With critical bacteria at the facility that cannot survive for more than a few hours during a power outage, Delorean required a full-proof solution that could act as a UPS (uninterrupted power supply) and guarantee continuous reliable power.
What Needed to be Powered
Pumps, motors, control systems, and ancillary equipment needed to test, commission, and operate the plant prior to permanent grid connection.
Alternatives Assessed
The alternative considered was the use of a standalone diesel generator operating 24/7, coupled with a larger back-up generator to manage peak loads due to the criticality of the project. This option was considered less reliable than a hybrid BESS-generator solution, as it did not offer remote monitoring capability, and was more expensive.
THE POWERSHIFT SOLUTION

POWRBANK MAX units are a large-scale mobile battery system designed for high-powered and long-duration commercial, industrial and grid applications
THE HIGHLIGHTS
The POWRBANK MAX delivered reliable, uninterrupted temporary power, keeping the site online even when the generator required maintenance. Acting as a dependable backup and load support solution, with 24/7 monitoring and support, it gave the customer complete peace of mind knowing power was always available when it mattered most.
24/7 Remote Support
With continuous remote support, potential issues were identified and resolved early, preventing site disruption and delivering peace of mind.
Reduced Risk of Downtime
The system safeguarded the site against unexpected power interruptions, protecting critical operations.
Uninterrupted Power Delivery
The site remained online, including during generator outages and maintenance periods.
Set-and-Forget Solution
Once deployed, the system operated reliably in the background, removing the need for constant on-site intervention from the customer.
“At Delorean Corporation, we design, build, commission, and operate Waste to Energy facilities and the BESS from Powershift was of great help to our project in Lilydale, Victoria. We utilised the 300kW BESS unit from Powershift during the late construction and the commissioning stage of this project. During early construction, the site was powered only by diesel gensets and by March 2025, the site required more power, and the fuel expense was increasing. Once we received the BESS on site, it was connected to temporary distribution boards during construction to supply power to critical equipment required to run 24/7, to recharge EWPs, and to power construction lighting. By October 2025, we started the commissioning stage for the facility and having the BESS on site allowed us to smoothly commission equipment ranging from 2kW to 200kW.
The BESS from Powershift was reliable and it was able to handle large loads without any issues. Thanks to the Powershift Team, especially Carl, for the smooth commissioning of the BESS and 24/7 online monitoring and support. Any external issue affecting the BESS was notified to us immediately and was resolved within the hour. This gave us peace of mind during the commissioning stage of our project, especially over the Christmas holidays when the site was not manned.
The cost savings on the diesel combined with the BESS’ small footprint, its plug and play style, and excellent support from Powershift made the whole experience great and will contact them for our next project!”
– Delorean Corporation