SNAPSHOT: Powershift delivered silent, reliable temporary power that enabled multiple new large housing developments to tenant homes on time, despite significant permanent power delays.
Customer
CV Services, Huff Group, Stockland, AVID Group
Application
Construction, Delayed Grid Connection
Location
Multiple across South East QLD
THE BRIEF
Problem We Helped Solve
Grid operator delays to connect permanent power prevented developers from energising new homes across several SEQ estates—creating project delays, increased holding costs and risk to tenancy timelines. Diesel generators were not suitable due to residential noise restrictions, high fuel costs, maintenance requirements and unreliability.
What Needed to be Powered
Between 20–55 newly constructed homes per site, staged over several months as homes became due for settlement.
Alternatives Assessed
The only alternative was to wait up to six months for permanent grid power and delay settlements, as generators are not an appropriate or reliable option for these customers.
THE POWERSHIFT SOLUTION

POWRBANK MAX units are a large-scale mobile battery system designed for high-powered and long-duration commercial, industrial and grid applications
THE HIGHLIGHTS
Across all sites, the POWRBANK MAX delivered consistent, dependable performance throughout both final construction and occupancy of new homes. Each deployment ensured developers, contractors and incoming residents had access to stable, quiet temporary power that was hassle free, keeping tenancy timelines on track.
Satisfied Tenants
Enabled developers to tenant and settle homes on schedule, avoiding delays caused by grid connection wait times.
Eliminated Noise
Delivered quiet, clean and emission-free temporary power compliant with residential environments.
Uninterrupted Power
Residents experienced reliable, uninterrupted power throughout their occupancy while the battery was on site.
Reduced Costs
Eliminated the need for diesel generators—reducing costs, noise, refuelling and maintenance.