Customer


Decode

Application


Construction

Location


Cronulla, NSW

Problem We Helped Solve


Decode needed a reliable power solution to run a large demand from a very small grid supply and on a very tight site.

The requirements was to power over 700A of equipment – two tower cranes, two hoists, a tower boom and site general power – from only a 63A supply. With almost no space on site, the BESS unit also needed to be placed in the basement. Powershift was able to service this need with a single P300 unit, replacing what would otherwise have required three separate generators.

Power availability on site also changed as the project progressed, at times dropping below the standard 63A TBS supply, so Powershift worked closely with the Decode team to monitor loads in real time and ensure the site never lost power.

  • Powershift deployed 1 x P300 BESS unit, powering a DB feeding two tower cranes, two hoists, a tower boom and site general power from a 63A TBS input.
  • The compact, fume-free unit made it a safer option for placement in the site’s basement, removing the risks associated with running a diesel generator in an enclosed space.
  • The system was configured with the flexibility to accommodate additional loads as the project progressed. As power availability on site changed, at times dropping below the standard 63A TBS supply, Powershift worked closely with the Decode site team to reassess the BESS configuration, monitor loads in real time and ensure the site never lost power.

P300 units are highly compact, plug-and-play battery systems specially designed to power high peak electric machinery such as cranes, hoists, booms, welders and more.

The P300 delivered a single, streamlined power solution for Decode’s Cronulla site, replacing a three-generator setup while cutting both costs and emissions.