OFF-GRID SOLUTION FOR MAINS-DELAYED INDUSTRIAL BUILD
Read more: OFF-GRID SOLUTION FOR MAINS-DELAYED INDUSTRIAL BUILDSNAPSHOT: A Powershift battery, combined with a small generator, enabled McNab to commence their industrial build on-time despite no mains connection, without the need to run a generator 24/7. The hybrid solution delivered cleaner, quieter power…
-

BOOSTING INSUFFICIENT TEMP BUILDING SUPPLY ON HIGH-RISE CONSTRUCTION SITE
Read more: BOOSTING INSUFFICIENT TEMP BUILDING SUPPLY ON HIGH-RISE CONSTRUCTION SITESNAPSHOT: A single, pallet-sized battery from a 32A temp feed supported over 600A of equipment on a residential high-rise building project in place of multiple diesel generators.
-

DELIVERING RELIABLE TEMPORARY POWER SOLUTIONS TO KEEP ESSENTIAL CONSTRUCTION EQUIPMENT OPERATING
Read more: DELIVERING RELIABLE TEMPORARY POWER SOLUTIONS TO KEEP ESSENTIAL CONSTRUCTION EQUIPMENT OPERATINGSNAPSHOT: A Powershift BESS supplied reliable power to key construction equipment on a large Gold Coast high-rise construction site, including the essential dewatering system, along with a crane, hoist and site power, from only an 80A…
-

AN INNOVATIVE TEMP POWER SOLUTION FOR SEAMLESS COMMISSIONING AND OPERATIONS
Read more: AN INNOVATIVE TEMP POWER SOLUTION FOR SEAMLESS COMMISSIONING AND OPERATIONSSNAPSHOT: Jetcharge worked with Powershift to power the final stages of their Kinetic Electric Bus Depot, using a mobile battery to enable staged commissioning and maintain full site operations until permanent power was connected.
-

OVERCOMING GRID CONSTRAINTS WITH MULTIPLE STAGED BATTERY SOLUTIONS
Read more: OVERCOMING GRID CONSTRAINTS WITH MULTIPLE STAGED BATTERY SOLUTIONSSNAPSHOT: A 19-storey hotel in Melbourne’s CBD faced significant delays to construction and final handover due to delays with permanent grid power. To keep the final stages of construction moving and allow all areas of the…
-

POWERING PEAK LOADS WITH A SMALL TEMP BUILDING SUPPLY
Read more: POWERING PEAK LOADS WITH A SMALL TEMP BUILDING SUPPLYSNAPSHOT: Powershift delivered a compact temporary power solution for a space-constrained construction site in the heart of Adelaide that didn’t have enough TBS to run peak loads throughout the project.