Delivering reliable temporary power solutions to keep essential construction equipment operating
A Powershift BESS supplied reliable power to key construction equipment on a large Gold Coast high-rise construction site, including the essential dewatering system, along with a crane, hoist and site power, from only an 80A TBS feed.
The challenge
Gowdie Management Group were facing significant challenges due to a limited temporary building supply of just 80A on a tight Gold Coast construction site, with demand for over 600A of equipment across crane, hoist, site sheds, and temporary building power – as well as a 24/7 dewatering system.
What needed to be powered
- 1 × 250A Crane
- 1 × 160A Hoist
- 12 Site sheds and temporary building power
- 24/7 Dewatering system
The alternative
Multiple diesel generators — at least 2 × 300kVA, plus a back-up genset for the dewatering.
The solution
- The Powershift team presented a range of tailored solutions to demonstrate the versatility of integrating a battery on site, giving Gowdie the confidence to move forward with a solution that best met their operational needs.
- Deployed a Powershift Enertainer BESS unit charging from 80A of TBS to power all on-site equipment, with a genset back-up triggered via ATS (automatic transfer switch) should grid supply be lost, to ensure dewatering is always taken care of.
- 24/7 monitoring and support by Powershift ensured the battery delivered consistent, reliable power throughout the project, giving the customer peace of mind.
-
APEX and Enertainer Series
Enertainer L+
Heavy-duty power for large-scale demands
- Continuous
- 437kVA / 607A
- Peak
- 525kVA / 730A
- Storage
- 449kWh
Gensets are old school. Powershift is the next generation
The highlights
- No DieselBy switching to a battery solution, the site removed diesel entirely (except in the case the back-up genset is ever triggered) —cutting emissions, eliminating fuel deliveries, and creating a cleaner, safer worksite.
- Eliminated NoiseConstruction is taking place in a built-up holiday area, so removing a diesel generator significantly reduces noise levels and helps maintain a more community-friendly environment.
- Uninterrupted PowerThe battery system provides consistent, reliable power for all essential construction equipment, including the critical dewatering system, ensuring the project continues without interruption.
- Significant Cost SavingsEliminating the need for a generator to run 24/7 delivered $10k+ savings a month for the customer, reducing fuel costs, maintenance, and ongoing servicing expenses.
Project location
Gold Coast, QLD
Case studies
Proven on site
Ready to make the shift?
Start your hire today.
Tell us about your site and your loads, and our team will come back to you with a battery solution sized to the job. Not sure what you need or where to start? Get in touch via the General Enquiries options below and a team member will walk you through it!
GENERAL ENQUIRIES
For general enquiries, reach out through our contact form and one of our team will be in touch as soon as possible. Alternatively you can email us on info@powershift.tech or call your local team:
Australia: 1300 705 793
New Zealand: 09 872 0328,
TECHNICAL SUPPORT
Are you an existing customer needing technical and/or product support? You can email us at, support@powershift.tech. Otherwise call your local team:
Australia: 1300 038 400
New Zealand: 09 871 8585